The function of electric car charging piles is similar to that of gasoline pumps at gas stations. They can be fixed on the ground or wall and installed in public buildings (public buildings, shopping malls, public parking lots, etc.) and community parking lots or charging stations, and can be used to charge various types of electric vehicles according to different voltage levels.
The input end of the charging pile is directly connected to the AC power grid, and the output end is basically equipped with a charging plug to charge electric vehicles. Most charging piles are equipped with conventional charging and fast charging. You can use a specific charging card to swipe the card on the human-machine interface provided by the charging pile to do the corresponding charging mode, charging time, data printing and other operations. The charging post display can show the charging amount, charging time and other data.
Technical requirements for our AC charging posts

1. Requirements for environmental conditions
① Operating ambient temperature: -20℃~+50℃;
② Relative humidity: 5% to 95%;
③ Altitude: ≤1000m;
④ Installation location: outdoors;
⑤ Seismic capacity: Horizontal ground acceleration 0.3g;
⑥Vertical ground acceleration 0.15g;
2. Structural requirements
① The AC charging post housing should be sturdy;
② It shall be constructed in such a way that the exposed parts are not easily accessible by hand;
③The AC charging pile shall be selected as a steel combination structure with a thickness of 1.0 or more, with the surface treated by plastic dipping and with due consideration given to the requirements for heat dissipation. The charging pile shall have good shielding function against electromagnetic interference;
④ Charging piles shall have adequate support strength, necessary facilities shall be provided to ensure that the equipment can be properly lifted, transported, stored and installed, and holes for ground bolts shall be provided;
⑤ The bottom of the pile shall be fixedly installed on a base not less than 200mm above the ground. The area of the base should not be larger than 500mm x 500mm;
⑥ The pile shell shall be made of materials with strong impact resistance, good anti-theft performance and anti-aging;
3. Power requirements
① Input voltage: single-phase 220V;
② Output power: single-phase 220V/5KW;
③ Frequency: 50Hz±2Hz;
④ Allowable voltage fluctuation range is: single-phase 220V±15%;
4. Electrical requirements
① When the correct connection between the plug and the socket is confirmed, the separable circuit with load can be closed to realize the power supply to the socket;
② Leakage protection devices should be installed on the incoming side of the power supply cable;
③ The protection of low-voltage power distribution equipment and lines shall meet the relevant provisions in the Code for Low-Voltage Power Distribution Design (GB/50053);
④ For IT system distribution lines, when the first ground fault occurs, an acoustic or light signal shall be issued by the insulation monitoring device, and the faulty circuit shall be cut off by the overcurrent protection appliance or leakage current action protector when the second heterogeneous ground fault occurs;
⑤ In the lighting distribution system, lighting and socket circuits should not be supplied by the same circuit. The power supply side of the socket circuit shall be equipped with a residual current action protection device with a rated action current of 30mA;
5,Security protection function
① The AC charging pile shall be equipped with an emergency stop switch, which can be used to stop charging in an emergency by means of manual or remote communication;
② AC charging pile should have leakage protection on the output side;
③ AC charging pile should have output side over-current and short-circuit protection function;
④ AC charging posts shall be flame retardant;
6,IP protection grade
The AC charging post should comply with IP54 (outdoors) and be equipped with the necessary rain and sun protection;
7,Anti-corrosion (anti-oxidation) protection
Charging pile iron shell and exposed iron bracket, parts should take double layer anti-rust measures, non-ferrous metal shell should also have anti-oxidation protective film or anti-oxidation treatment;
8,Anti-theft protection
Anti-theft locks should be installed on the stake enclosure door, and bolts securing the AC charging stake must be installed or removed only after the enclosure door has been opened;
Group profile
ZHUHE Group is a diversified enterprise dedicated to providing high-quality, high-performance and high-value products and services to customers worldwide. We have strong production capacity and core technology advantages in a number of fields, and are unique in the electronics and new energy fields.

We emphasize on technological innovation and R&D investment to continuously improve production capacity and product quality. In the field of electronics, we have advanced intelligent factories, high-end automation equipment, professional technical team and perfect quality management system, which can provide customers with a full range of electronic solutions. Meanwhile, in the field of new energy, we have a first-class solar chip production line and a professional new energy project development team, which is committed to providing people with more sustainable and cleaner energy solutions.

Adhering to the concept of "technological innovation, integrity management, customer first", we always adhere to the business philosophy of high quality, high efficiency and high responsibility. Our products and services have been widely recognized and praised by customers, and have occupied an important position in the international market.
We have continued to develop markets, grow bigger and stronger, and actively expand our business in the electronics and new energy sectors, and have established a good brand image among our customers around the world. We are confident and capable of further utilizing our group's strengths and innovative capabilities to bring better products and services to the world.

Q:How much time does it take a car to charge?
A:The charging time for an electric car is dependent on the size of the car's battery and the charging speed of the carport. The bigger your car's battery, the longer it takes to charge from empty to full.
A typical electric car with 60kWh battery takes about 8 hours to charge from empty to full with a 7kW charging point.
Q:The Difference Between EV Charging Stations and EV Charging Piles?
A:Electric car charging stations are stations where electric cars are charged, which are similar to gas stations today. Charging stations can be divided into four sub-modules according to their functions: distribution system, charging system, battery scheduling system and charging station monitoring system. Charging stations are generally divided into three ways to charge cars: ordinary charging, quick charging and battery replacement. The regular charging is AC charging using 220V or 380V voltage. The quick charging is mostly DC charging. The main equipment of the charging station includes charging machines, charging piles, active filter devices and power monitoring systems.
Public electric car charging stations and electric car charging piles are two concepts. Electric car charging piles are fixed on the ground, and they provide AC electric energy for electric cars with on-board chargers by using special charging interface and conduction mode. They have corresponding communication, charging and safety protection functions.
Hot Tags: electric car charging piles, China electric car charging piles manufacturers, suppliers, factory, ,